New Construction On Grand River West Of Ingersoll
Sign up for eNotification updates on City Construction Projects
ENGINEERING PROJECTS
For more information on Engineering Projects:
WDM Engineering Services Department, City Hall
4200 Mills Civic Parkway, Suite 2D
P.O. Box 65320
West Des Moines, Iowa 50265
Phone: 515-222-3475
Grand Avenue Reconstruction - 1st Street to 5th Street
Booneville Road Reconstruction SW 100th Street to 115th Street
Ashworth Road Phase 4 - 88th Street (South) to 88th Street (North) & Bridges over I-80
88th Street Reconstruction - Ashworth Road to Abram Drive
2021 PCC Reconstruction Program (Vine Street 12th Street to 14th Street)
South Grand Prairie Parkway - Mills Civic Parkway to Stagecoach Drive
South Grand Prairie Parkway - Stagecoach Drive to Grand Avenue
Grand Avenue West Segment 5B and 7A Sewers
Grand Avenue - Grand Prairie Parkway to South 115th Street
West Grand Business Park & Booneville Road
Booneville Road Bridge over Johnson Creek
SE County Line Road
Holiday Park Access Road
Holiday Park Little League Stormwater Pump Station Relocation
South 35th Street and Grand Valley Culvert Replacement
Sugar Creek Conveyance Improvements Phase 2
2021 PCC Patching Program
2021 HMA Resurfacing Program
Engineering Services YouTube Channel - Drone videos of construction projects
| Project | Information | Updated |
|---|---|---|
| SUGAR CREEK CONVEYANCE IMPROVEMENTS PHASE 2 | Estimated Start: Winter 2020 Estimated Completion: Fall 2021 Contractor: PCI Project Overview: The project will include the grading of Sugar Creek from Raccoon River Drive bridge to the confluence of the Raccoon River. The stream grading includes re-grading the foreslopes of the stream as well as grading a floodplain bench on the south side of the stream. Construction activities will include tree clearing, grading, placement of revetment, surface restoration, and all other related work. Project Status: The contractor has substantially completed the project and will be working on punch list items. Vicinity Map of the Project Drone Flyover of the Project | 12/10/2021 |
| Ashworth road phase 4 - 88th street (South) to 88th street (north) & bridges over i-80 | Estimated Start: Spring 2021 Estimated Completion: 240 Working Days Contractor: Jensen Construction Co. Project Overview: The project is being administered by Iowa Department of Transportation. The scope of the project includes constructing two new bridges over I-80 and removing the existing bridge. They will be constructing the necessary storm sewer and paving connecting the prior Ashworth Road projects. Project Status: The contractor has placed fill material for the bridge, installed water main and storm sewer. They have poured the eastbound bridge deck and continue to work on the bridge rail. Posted Detour Map for Ashworth Road Closure Starting Monday, August 16th at 6:00 am Ashworth Road Overall Plan Layout Vicinity Map of the Project Drone Flyover of the Project | 12/10/2021 |
| grand avenue reconstruction 1st street to 5th street | Estimated Start: April 19 2021 Estimated Completion: Late Fall 2021 Contractor: Corell Contractor Project Overview: The project will remove all existing pavement and widen the roadway from 1st Street to just east of 5th Street. There will be storm and sanitary sewer improvements along the corridor. Project Status: Grand Avenue will be reopened to through traffic by December 17th. Grand Avenue Overall Plan Layout Stage 1 Plan Vicinity Map of the Project Drone Flyover of the Project | 12/10/2021 |
| holiday park little league stormwater pump station relocation | Estimated Start:Spring 2021 Estimated Completion:Spring 2022 Contractor: Corell Contractor Project Overview:Construct Holiday Park Little League Stormwater Pump Station Relocation including all labor, material and equipment necessary to construct approximately 488 linear feet of storm sewer in open cut 15-inch and 16-inch, 538 linear feet of force main, 12-inch in open cut, drain manhole, storm manholes, storm intakes, sediment manhole 2 pump submersible pump station, electrical and control, excavation, backfill, connections to existing sewers, abandonment of existing storm sewers, surface restoration, traffic control and miscellaneous associated work, including cleanup. Project Status: The contractor has a few fence replacement items to complete as well as punch list items. Vicinity Map of Project Drone Flyover of the Project | 12/10/2021 |
| 2021 pcc patching program | Estimated Start:Spring 2021 Estimated Completion:Fall 2021 Contractor: Shekar Engineering Project Overview: Portland Cement Concrete (PCC) Patching at various locations including approximately 215 LF of PCC curb and gutter replacement, 596 SY of reinforced 7" PCC full depth patching, 359 SY of reinforced 8" PCC full depth patching, 5000 SY of reinforced 9" PCC full depth patching, 235 SY of reinforced 7" PCC full depth patching (IA DOT 5 Hr. PCC Mix), 266 SY of reinforced 8" PCC full depth patching (IA DOT 5 Hr. PCC MIX), 2296 SY of reinforced 9" PCC full depth patching (IA DOT 5 Hr. PCC MIX), 40 SY of PCC partial depth patching, median repair, intake reconstruction, manhole adjustments, drives, sidewalks, traffic control, traffic loops, and other miscellaneous work to complete the project. Project Status:The contractor is finishing the remaining patches this week. They are working on EP True Pkwy east of Valley West Dr. Vicinity Map of Project Drone Flyover of the Project | 12/10/2021 |
| 2021 hma RESURFACING program | Estimated Start:Spring 2021 Estimated Completion:Fall 2021 Contractor: Des Moines Asphalt Project Overview:This project will resurface various locations in the City of West Des Moines. Types of work including approximately 165 tons of HMA HT ½" leveling course, 1,880 tons of HMA interlayer, 2,822 tons of HMA ½" intermediate course, 7,798 tons of HMA HT ½" surface course, 51,922 square yards of surface milling, 35,360 linear feet of crack cleaning and filling, 5,234 square yards of PCC M-4 Mix full depth patching, 594 square yards of PCC 5-Hour Mix full depth patching, 1,093 square yards of PCC sidewalk, 1,228 linear feet of PCC curb and gutter, fixture adjustments, pavement markings, traffic control, and miscellaneous work to complete the project. Project Status:The contractor will suspend work for the winter and complete the handicap sidewalk ramps in the spring of '22. Public Notice to the Ashworth Road Residents Vicinity Map of Ashworth Road Resurfacing Drone Flyover of the Project | 12/10/2021 |
| 88th street reconstruction ashworth road to abram drive | Estimated Start:Summer 2021 Estimated Completion:Summer 2022 Contractor: Alliance Construction Project Overview:Construction of the unpaved sections of 88th Street from Abram Drive to Ashworth Road including 5,000 CY of Topsoil, 2,140 CY of Excavation, 10,505 CY of Contractor Supplied Embankment in Place, 13,024 SY of Subgrade Preparation and 13,024 SY of Granular Subbase. 1,935 LF of Storm Sewer and 29 Storm Sewer Structures. 875 LF of Water Main, 2,948 LF of Subdrain, and Subdrain Outlets. 11,026 SY of 9.5inch Reinforced PCC Pavement, 849 SY of 6 inch Reinforced PCC Trail and 1,320 SY of PCC Driveway. Clearing and Grubbing, Traffic Control, Construction Survey, Erosion Control, Pavement Markings, Seeding, and other Miscellaneous Construction. Project Status: The contractor has reopened the paved section of 88th Street between EP True Parkway and Century Drive. The contractor completed the underground utility work on stage 2 just south of Ashworth Road but were delayed by utility conflicts and were not able to pave the road back this fall. The road surface has been returned to gravel and reopened to traffic. This section will be closed in the spring of '22 and paved. This segment is expected to be paved by late May. Stage 3 will be delayed until spring of 2022. Vicinity Map of Project Drone flyover of the Project | 12/10/2021 |
| south grand prairie parkway mills civic parkway to stagecoach drive | Estimated Start:Spring 2021 Estimated Completion:Fall 2022 Contractor: CTI Project Overview: Project Description The paving, grading and drainage associated with a future roadway, SW Grand Prairie Parkway from Mills Civic Parkway to Stagecoach Drive. Project includes 118,000 CY of earthwork, 19,000 SY of paving, 3,700 LF of RCP Storm Sewer, 3,500 LF of Water Main, two single-barrel 10' x 9' reinforced concrete box culvert totaling 670 LF, 10700 LF of open-access conduit network and erosion control. Project Status:The contractor has paved Stagecoach Drive from South 100th Street to Grand Prairie Parkway. This section will remain closed to the public over the winter but will remain open for a construction entrance to the Grand Prairie Parkway portion of the project. Utility work and grading on Grand Prairie Parkway have been completed for this year. Overall Plan Sheet of Grand Prairie Parkway and Stagecoach Drive Vicinity Map of Project Drone flyover of the Project | 12/10/2021 |
| west grand business park & booneville road | Estimated Start: Spring 2021 Estimated Completion:Fall 2021 Contractor: Alliance Construction Project Overview: Extension of Raccoon River Drive from Grand Avenue to Booneville Road, reconstruction of Booneville Rd and reconstruction of Glen Oaks Drive, involving earthwork paved roadways and storm sewer, including all materials labor and equipment necessary for the project including the approximate quantities: 9464 SY PCC pavement, 18,000 CY earthwork, 3300 LF of storm sewer pipe. Project Status:Booneville Road is closed from Glen Oaks south drive to the west 500'. The contractor has completed the general site grading and underground utility work on much of the project. Paving has been delayed until spring of '22. Overall Plan Sheet of West Grand Business Park Vicinity Map of Project Drone flyover of the Project | 12/10/2021 |
| BOONEVILLE ROAD RECONSTRUCTION S. 100TH STREET TO S. 115TH STREET | Estimated Start: Spring 2021 Estimated Completion:Summer 2022 Contractor: Absolute Concrete Project Overview:This project will include construction of Booneville Road from South 100th Street to South 115th Street. The construction improvements include approximately 21,560 SY of 8-inch, 10-inch, and 12-inch PCC reinforced pavement and 6-inch PCC driveway pavement, storm sewer, watermain, fiber conduit interconnect, subdrain, pavement markings, clearing and grubbing, grading, soil stabilization, traffic control, erosion control, surface restoration, and miscellaneous associated work to complete the project. Project Status:The contractor is grading and installing underground utilities. Paving is planned for spring of 2022. Overall Plan Sheet of Booneville Road Vicinity Map of Project Drone flyover of the Project | 10/11/2021 |
| SOUTH GRAND PRAIRIE PARKWAY - STAGECOACH DRIVE TO GRAND AVENUE | Estimated Start:Summer 2021 Estimated Completion:Fall 2022 Contractor:McAninch Corporation Project Overview:The paving, grading, and drainage associated with a future roadway, South Grand Prairie Parkway from Grand Avenue to Stagecoach Drive. Project includes 275,000 CY of earthwork, 28,000 SY of PCC roadway paving, 7,500 SY of PCC trail, 11,000 LF of RCP storm sewer, 6,500 LF of water main, 20,000 LF of open access conduit, traffic control, erosion control, pavement markings, and site restoration. Project Status:The contractor is grading the site so underground utilities may be installed. Underground utility work is planned to occur throughout the winter months or until winter weather prohibits. Vicinity Map of Project Drone Flyover of the Project | 10/11/2021 |
| grand avenue west segment 5b and 7a sewers | Estimated Start:Summer 2021 Estimated Completion:Winter 2021 Contractor: Rognes Corporation Project Overview:Construct Grand Avenue West Segment 5B and 7A Sewers including all labor, material and equipment necessary to construct approximately 8,970 LF of sanitary sewer in open cut 15-inch thru 36-inch diameter, 125 LF of 15-inch sanitary sewer tunneled in place, manholes, excavation and backfill, connection to existing manhole, connection of existing force main, abandonment of existing 12-inch force main, erosion control, surface restoration, traffic control and miscellaneous associated work, including cleanup. Project Status:The contractor is installing the trunk sewer along the future Grand Avenue corridor. Vicinity Map of Project | 10/11/2021 |
| GRAND AVENUE - South GRAND PRAIRIE PARKWAY TO SOUTH 115TH sTREET | Estimated Start:Fall 2021 Estimated Completion:Fall 2022 Contractor:Elder Corporation Project Overview:The project includes the construction of PCC pavement, related storm sewer, sanitary sewer, water main, subdrain, earthwork, channel excavation, and SWPPP controls generally located west of the future intersection of South Grand Prairie parkway and Grand Avenue. Project Status:The contractor is working on underground utilities. Vicinity Map of Project Drone Flyover of the Project | 12/10/2021 |
| BOONEVILLE ROAD BRIDGE OVER JOHNSON CREEK | Estimated Start:Fall 2021 Estimated Completion:Summer 2022 Contractor:Iowa Bridge & Culvert Project Overview:The project will include construction of Booneville Road Bridge over Johnson Creek. The construction improvements include construction of a 120' -0x47' -2 continuous concrete slab bridge, bridge, approach pavement, bridge monuments, PCC shared use path, 10'x5' precast concrete culvert with headwalls, grading, soil stabilization, traffic control, erosion control, surface restoration, and miscellaneous associated work to complete the project. Project Status:The contractor is working on the substructure of the bridge. Vicinity Map of Project | 12/10/2021 |
| SE COUNTY LINE ROAD | Estimated Start:Fall 2021 Estimated Completion:Fall 2022 Contractor:Elder Corporation Project Overview:The construction update includes approximately 53,620 CY of earthwork, 16,564 SY of concrete paving, 7,045 SY of concrete shared use path, 986 SY of concrete driveway, 4,229 LF of storm sewer, 4,549 LF of subdrain, 4,634 LF of water main, drainage structures, 144 LF pedestrian tunnel, traffic control, pavement markings, erosion control, and other associated work. Project Status:The contractor continues grading the site and is working on underground utility installations. Vicinity Map of Project Drone flyover of the Project | 12/10/2021 |
PARKS & RECREATION PROJECTS
For more information on Parks & Recreation Projects:
WDM Parks & Recreation Department, City Hall
4200 Mills Civic Parkway, Suite 1B
P.O. Box 65320
West Des Moines, Iowa 50265
Phone: 515-222-3444
Email: ParkRec@wdm.iowa.gov
WRA SUGAR CREEK STREAM CORRIDOR IMPROVEMENT PROJECT
JORDAN CREEK TRAIL RENOVATION (EP TRUE PKWY TO 50TH ST)
VALLEY VIEW PARK NORTH LOOP ROAD EXTENSION
RACCOON RIVER PARK EXTERIOR LED LIGHTING IMPROVEMENTS
2021 COURT IMPROVEMENTS
CROSSROADS PARK PARKING LOT AND WATER QUALITY IMPROVEMENTS
SUGAR CREEK GREENWAY TRAIL - PHASE 1
CROSSROADS PARK TENNIS COURT LIGHTING IMPROVEMENTS
| Project | Information | Updated |
|---|---|---|
| WRA SUGAR CREEK STREAM CORRIDOR IMPROVEMENT PROJECT | Estimated Start:Winter 2020 Project Status: Project is substantially complete. All native seed areas have been seeded and tree plantings are completed. For additional information see attachments: Vicinity Map Letter to property owners along Sugar Creek 03/03/20 Letter to property owners along Sugar Creek 12/10/19 Landscape and Trail Plan exhibit Sugar Creek Improvements, Phase 1 - Construction Documents Letter to property owners along Sugar Creek 09/04/20 Sugar Creek Greenway Trail Phase 1 - Construction Documents | 10/04/21 |
| JORDAN CREEK TRAIL RENOVATION | Estimated Start: Summer 2021 Project Status: Project is substantially complete and the trail is open. In Spring, trail may be closed intermittingly to complete remaining punch list items. Click here for a vicinity map. | 11/22/21 |
| VaLLEY VIEW PARK NORTH LOOP EXTENSION | Estimated Start: Spring 2021 Estimated Completion: Summer 2021 Contractor: Absolute Concrete Specialist Project Overview: Extension of the north loop road approximately 600 LF to the east. The road is being extended to provide access and parking for a future outdoor pickleball court complex to be located generally in northwest corner of the park. The pickleball complex is anticipated to be completed in Spring 2022. This current phase includes grading, utilities, and pavement of the road and is anticipated to be completed later this summer. Project Status: Project is substantially complete. Click here for a vicinity map | 11/22/21 |
| RACCOON RIVER PARK LED LIGHTING IMPROVEMENTS | Estimated Start: Fall 2020 Project Status: Project is substantially complete. Click here for a vicinity map | 10/04/21 |
| 2021 COURT IMPROVEMENTS | Estimated Start:Summer 2021
Project Status: Project is substantially complete. Click here for a vicinity map | 11/22/21 |
| CrossROADS PARK PARKING AND WATER QUALITY IMPROVEMENTS | Estimated Start: Fall 2021
Project Status: Contractor has completed grubbing and clearing of vegetation along creek channel. New parking stalls near tennis court complex also complete. Contractor currently performing grading operations along creek channel. Please note trail access through park will be closed during construction. In the Spring, park access will need to be closed for several days inorder to complete asphalt overlay. More information will be provided once the work has been scheduled. Click here for trail closure map | 11/22/21 |
| SUGAR CREEK GREENWAY TRAIL - PHASE 1 | Estimated Start:Fall 2020 Project Status: Project is substantially complete. For additional information see attachments: Vicinity Map Sugar Creek Greenway Trail Phase 1 - Construction Documents | 11/22/21 |
| CROSSROADS PARK TENNIS COURT LIGHTING IMPROVEMENTS | Estimated Start: Summer 2021 Estimated Completion: Summer 2021 Project Status: Project is substantially complete and push-button activators have been installed. Lights are programmed to activate from dusk to 10:00pm for 30 minute intervals. Click here for a vicinity map | 11/22/21 |
Posted by: marilynrpolornetess.blogspot.com
Source: https://www.wdm.iowa.gov/residents/streets-construction/construction-updates